Sports Complex Park Trail Improvement Project

This in-house design project includes the design, permitting and construction of the Sports Complex Park Trail Improvement project, which includes the replacement of the existing, perimeter eight (8) ft wide, asphalt walkway/trail path (approximately 3500 LF) with a new eight (8) ft wide concrete walkway/trail path. The proposed work shall include removal & disposal of existing asphalt walkway/trail path, re-working existing base, sub-base, backfilling, grading, compaction site preparation, concrete placement, site restoration and associated improvements. The proposed improvements aim to enhance the appearance and integrity of the walkway/trail path at the Sports Complex while supporting the City’s Strategic Goal #1, “Tamarac is Home” and Goal #4, “Tamarac is Vibrant” through the proposed improvements of the park

This project is part of the Recreational Trails Program (RTP), and awarded a Federal Grant administered by the Florida Department of Environmental Protection (FDEP) for approximately eighty (80) % grant funding with a twenty (20) % match of local funds as approved via Resolution No. R-2023-030.

DISTRICT:District 3
ESTIMATED START DATE:Spring 2025
ESTIMATED COMPLETION DATE:Fall 2025
ESTIMATED COST:$385,000.00
STATUS:COMPLETED


Project Development Roadmap

Note: Explore the journey — click on each milestone to see what’s been accomplished.

BID Process
BID was awarded
Phase 1 -3 Completed
Phases 1 thru 3 of the path are complete
Phase 4 Ongoing
Concrete pads requested
BID Process
The project has been through the City’s competitive bidding process and was awarded during the September 25, 2024, Commission meeting.
BID Process
Phases 1 thru 3 of the path are complete
Phases 1 through 3 of the path have been successfully completed, marking significant progress in the overall project.
Phases 1 thru 3 of the path are complete
Phase 4 Ongoing
The contractor is completing concrete work for phase 4, and when finished, will begin work on the final phasework. The contractor has submitted a change order to install three (3) concrete pads, requested by the Parks and Recreation department for the future installation of benches along the path.